£7.7m project to protect River Wharfe gets underway in Leeds village
The works are set to be complete in 2028
Yorkshire Water has begun work on a new wastewater reduction project in Boston Spa, with a view to improving the overall health of the River Wharfe.
Once completed, the scheme will see the installation of a new underground storage tank to hold excess rainwater and wastewater within the sewer system during stints of bad weather.
Other projects in Leeds are also in progress in Kirkstall, Headingley, Armley, Farsley, and Morley.


The structure will allow Yorkshire Water to reduce strain on the network’s capacity during bouts of heavy rainfall - when capacity returns to normal, excess wastewater and rain will be sent to treatment works along the river.
Contract partners Ward and Burke expect construction to take around 19 months, hoping to reduce sewer overflow events by 60%.
Dale Crapper, Project Manager at Yorkshire Water, said: “Across Yorkshire, we're spending £1.5bn between 2025 and 2030 on reducing the frequency and duration of discharges from our storm overflows.
“We currently have schemes underway in Bradford, Calderdale, and Huddersfield, as well as in North and South Yorkshire, and this scheme in Boston Spa is the 17th project underway in Leeds. We're excited to be getting this one started.”
The storm overflow project is part of Yorkshire Water’s £8.3bn investment into its services and the environment over the next five years.